FCC Update – Shotton High Street improvements 09/03/2026

Overnight resurfacing works will continue and are anticipated to be completed by 2 April 2026. The road will remain open throughout, with traffic managed under a convoy system between 7:00pm and 7:00am.

Daytime traffic management will resume during the week commencing 23 March to enable continued progress which includes the replacement of bus shelters, removal of unnecessary barriers, and the introduction of dedicated right-turn pockets at key junctions on Charmleys Lane, Chester Close, Nelson Street, and Jubilee Street.

Further improvements will also include upgrades to street lighting and traffic signals, as well as the replacement of benches, bollards, and bins across the area.

Regular updates can be found here:

https://www.flintshire.gov.uk/en/Resident/Streetscene/Shotton-High-Street-Works.aspx

Shotton High Street resurfacing Update

Resurfacing Programme

The first phase of resurfacing works — from the eastern side of Nelson Street to Shotton Lane, including the junction area — will be delivered under night-time convoy working arrangements between 7:00pm and 7:00am in order to minimise disruption during peak daytime traffic periods.

The resurfacing programme will comprise the following activities:

  • Removal of the existing carriageway surface
  • Ironworks adjustments, including the replacement and adjustment of covers and gulleys
  • Full carriageway resurfacing (currently programmed to commence on 24 March for a duration of three nights)
  • Traffic signal works (loop cutting) during the weekend of 27 and 28 March 2026
  • Two subsequent nights of road marking

Programme Notice

The dates outlined above reflect the current planned programme. However, works remain subject to change in the event of unforeseen circumstances, such as adverse weather conditions or unexpected site constraints.